– Design team – headed up by Lead Designer and overseeing the design programme – Client team – headed up by Project Manager and overseeing the project programme – Construction team – headed up by Project Director and overseeing the construction programme
Feasibility studies and site surveys may be required at this stage to test the brief against the chosen site and budget i.e. are there any access issues? Is it a sloping site? What is the spatial overview and relationships with neighbouring buildings? This is often the time for us to discuss options regarding the site with the local planning authority and make sure there are no constraints. We like to establish clear and positive communication with these departments from the outset. Discussions around building regulations and other legal requirements should happen at this stage including whether the site is within a listed buildings or conservation area It is at this point that objectives are finalised and recorded under:– Project Outcomes – Sustainability Outcomes – Quality Aspirations – Spatial Requirements
Working with the client, we will at the end of this stage, produce a timescale for the project as well as a project execution plan setting out delivery.– Interior and exterior renders – Landscaping – Specific requests – Strategic engineering requirements
There is as the RIBA states ‘no right or wrong approach’ at this point, it is our initial design response to the brief and will involve regular meetings, discussions and reviews with the client and specialist stakeholders including planners and those across structural and civil engineering, to shape and define it. The robust architectural concept along with the project brief and cost plan are signed off at the end of this stage. Stage Three – Spatial Co-ordination ‘The co-ordinated design takes form.’ Formerly the developed design stage, here our team draw up the client approved design in CAD or ever increasingly with BIM, and develop and test it alongside detailed structural design, outline specifications, building services and cost analysis to ensure its viability. Our design will incorporate the practical elements relating to:– Window, door, stairway, and fire exit locations – Fixtures, fittings – Proposed materials – Load bearing mechanical information – Mechanical, plumbing, and electrical considerations – Tech and security – Green, eco and solar
During this stage, or certainly at the end the design is finalised into a single model, not prone to change, and planning applications are ready for submission incorporating all our detailed drawings and reports. Stage Four – Technical Design ‘Final design stage before construction begins’ We make further refinements of the existing design at this stage, incorporating where relevant detail from specialist sub-contractors such as lighting specialists, kitchen designers or glazing companies. From this our Lead Architect prepares comprehensive drawings, specifications, and documents for tender. The level of detail will depend on the size and scope of the project but by the end of this stage all elements will be prescriptive rather than descriptive for the project to be manufactured and built, i.e., they set out detailed descriptions around the following:– Requirements relating to regulations and standards – The specific types of products and materials required – The methods of delivery and installation – The building systems in place i.e., flooring, partitions, mechanical and structural
At the end of this stage all information required to construct the project is completed and we send out the tender to 3-4 contractors we have worked with before. Of course, should the client want to add to the list we will do so. Stage Five – Manufacturing and Construction ‘All systems go…construction begins’ The design process is now complete and the appointed contractor takes possession of the site to carry out works as per the schedule of works and building contract. This includes manufacturing off-site and construction on-site. Stage four and stage five can overlap or run concurrently dependent on the size and scope of the project, or when the contractor was appointed. The client can choose to appoint us as the contract administrator at this point should they wish. In this role we act as the middle ground between the client and the contractor to ensure that all works are being done in accordance with finalised drawings and specifications. This can entail:– Chairing construction progress meetings – Preparing and issuing construction progress reports – Co-ordinating site inspections – Dealing with site queries – Agree reporting procedures for defects – Issuing project documentation to the client – Issuing certificates of completion
If appointed, we like to meet weekly with the client and the relevant parties to ensure that everything is running smoothly. The appointment of Building control by the client should take place, to oversee the project and ensure that all is in order in relation to the necessary construction standards. Health and Safety inspectors will review and observe the site at this stage, so it is worth considering an independent consultant to ensure that all the correct procedures are followed. Stage Six – Handover ‘The completed building is finished and handed over’ After practical completion, the building is ready for hand over to the client, and the building contract concludes. Feedback and building aftercare exercises take place during this stage to act as future learnings for ourselves, the client, contractor, and consultants, and to address any issues relating to the integrity of the building. These involve light touch post occupancy evaluation and snagging processes, whereby the client compiles a list of defects or incomplete works, overseen by us as the contracts administrator and presented to the contractor to rectify. They then have an agreed Defect Liability Period, usually six to twelve months to address these, after which if all has been made good, building control will sign off the construction and we will sign off the project as a whole. We then issue a final certificate, and this stage is complete. Stage Seven – Use ‘The vision for the building is realised and it is now in use’ This stage starts concurrently with stage six. The building is now occupied and in use. On most projects, our design team will have no duties to fulfil here. However, the incorporation of this stage into the RIBA Plan of Work 2020 gives the client the opportunity to get in touch with us if they require general advice relating to maintenance, energy consumption or management of the facilities. We welcome this communication as we love to hear how the client is finding their new building, and it also allows for effective aftercare, valuable feedback, and building monitoring especially around energy consumption, and is therefore key to the sustainability strategy. The addition of this feedback stage has made the Plan of Work cyclical as it unites the entire process into one, allowing for proper use of the building and then when demands change, and the building reaches an end of life where refurbishment or a new building may be needed, stage zero starts again. Embarking on a design and build project can often be a complex one for all involved, for a client it can be daunting. The RIBA Plan of Work 2020 offers all stakeholders a clear approach to map out the journey collaboratively from vision, through to design, construction and eventual use. At RISE Design Studios, we find that this straightforward process with realistic and measurable targets, the ability to review progress and a provision for valuable learnings allows for enhanced clarity, greater realisation of vision, and successful outcomes no matter the diversity of projects. For more information on the RIBA Plan of Work 2020 visit RIBA Plan of Work (architecture.com) If you would like to talk through your project with the team, please do get in touch at mail@risedesignstudio.co.uk or give us a call on 020 3290 1003.RISE Design Studio Architects company reg no: 08129708 VAT no: GB158316403 © RISE Design Studio. Trading since 2011.