How Much Does It Cost to Renovate and Extend a House in London in 2027?

The cost of renovating and extending a house in London depends on the condition of the house, how much of it you keep and the standard you build to. This guide works through a real cost plan from one of our projects, and shows where budgets usually go wrong.

Concept design illustration of a detached brick house in north London with a clay tile roof and two proposed curved single-storey extensions in textured buff brick, with curved glazing, perforated brickwork and a paved terrace with dining table and lavender planting. RISE Design Studio.

Concept design for the renovation and extension of a detached house in north London, with two curved brick wings opening onto the garden. RISE Design Studio.

It's the first question we're asked, and the hardest to answer in one line. Two houses of the same size on the same street can need very different amounts of work, because one needs new floors, wiring and windows throughout while the other only needs a new kitchen wing. So we start with a benchmark, then build the real number with you.

In the example below, a whole-house renovation and extension of a detached house in north London has a construction allowance of £1,007,032 at June 2026 prices. Across about 244 m² of gross internal floor area, that works out at £4,126 per m², or £383 per sq ft.

That figure includes the contractor's preliminaries, overheads and profit, and a contingency. It excludes VAT, professional fees and the other costs explained below. It's a benchmark for this scope of work, and a figure per square metre is only useful if you know what is inside it, so ask anyone who quotes one.

A real renovation and extension cost plan

Our quantity surveyor prepared this Stage 2 cost plan in June 2026. Stage 2 is an early design stage, so the estimate is there to test the proposals against the budget before the design is developed in detail. It is not a contract price.

The project combines renovation and extension with a deep retrofit of the existing house. The allowances include an insulated brick-slip cladding system, replacement windows, new windows and external doors, a heat pump, underfloor heating and mechanical ventilation with heat recovery (MVHR). The rate is calculated across the whole 244 m², including the retained house, and not just the extension.

Item Allowance
Enabling works: surveys, strip out, temporary support, demolition £35,000
Substructure: foundations, ground slab, drainage £58,050
Superstructure: steel, walls, cladding, roof coverings, stairs, windows, doors, partitions £381,485
Finishes: floors, walls, ceilings £73,970
Fixtures and fittings: kitchen, utility, sanitaryware, joinery, blinds £119,918
Building services: heat pump, underfloor heating, MVHR, plumbing, electrics £93,583
External works: paving, steps, gates, planting allowance £23,480
Building and external works £785,486
Main contractor's preliminaries £86,403
Main contractor's overheads and profit £87,189
Contingency at 5% £47,954
Total construction allowance, before VAT £1,007,032

 

The building and external works account for about 78% of the total, or roughly £3,220 per m². The contractor's allowances and the contingency make up the other 22%. Preliminaries cover the cost of running the site, including supervision, welfare and temporary facilities. They have to be paid for even though none of it becomes part of the finished house.

This is one reason two prices per square metre can look so different: they may describe different scopes or include different allowances. Our guide to the cost of extending your home in London looks separately at extension-only rates.

What changes the cost

1. The condition of the house. An existing building keeps its secrets until the strip out. Rotten joists, old wiring, shallow foundations and asbestos can all change the scope, and a measured survey won't show them. This cost plan excludes asbestos, underpinning, piled foundations and levelling the first-floor joists. If investigations show any of these are needed, they are priced and added to the budget.

2. How much you keep. Retaining sound parts of the house avoids the cost of replacing them, though keeping something rarely means spending nothing on it. The example includes £8,595 to upgrade the roof and loft insulation, and £1,500 to retain and reconnect the existing solar panels.

3. The size and shape of the extension. A simple rectangle is more economical than an extension with several corners, changes in level and long glazed openings. The cost sits in the foundations, structure and junctions as much as in the floor area gained. Here, foundations and the ground-floor slab carry £39,000, with £11,000 for below-ground drainage.

4. Opening up the house. Removing walls to connect old rooms to new ones needs structure and temporary support. The example allows £26,600 for structural steel and padstones, and £9,000 for propping. Those are useful figures to have in mind when deciding how open you want the plan to be.

5. Specification. Windows, kitchens, bathrooms and joinery give you the most control over the budget. Replacement windows are £85,500 and new windows and external doors are £64,000, which together is £149,500, close to 15% of the construction allowance. The kitchen joinery, worktop and appliances carry £50,370, and fitted joinery and wardrobes add £29,750. These are allowances for this design, not standard prices for every house.

6. The energy standard. A deep retrofit needs insulation, windows, airtightness, ventilation and heating designed together. The insulated cladding, heat pump, underfloor heating and MVHR in this example total £68,340. That is what those packages cost in this plan. It isn't the premium for a low-energy house, because the windows sit elsewhere and a conventional renovation would still need a heating system. EnerPHit, the Passivhaus standard for existing buildings, targets a heating demand of about 25 kWh per m² a year, and if certification is part of the brief it needs to be designed and budgeted for from the start.

7. Time. Prices move between the first cost plan and the start on site. BCIS currently forecasts tender prices rising by about 3% a year, which would take this estimate from £1.007m to about £1.037m over twelve months, before VAT. Keep the price date beside the figure. A June 2026 estimate should not quietly become a 2027 budget.

What sits outside the construction figure

The cost plan lists 39 exclusions, from loose furniture and feature lighting to air conditioning and work to the front drive. Each one needs a decision: it is either not needed, allowed for elsewhere, or something the client funds separately. These are the main additions.

  • VAT. Applying 20% to the full construction allowance adds £201,406, bringing it to £1,208,438.
  • Professional fees. Architect, structural engineer, quantity surveyor, services engineer and any specialists the project needs. Together, typically 12 - 20% of the construction cost.
  • Surveys and investigations. The plan includes £2,500. Check what that covers before adding allowances for a measured survey, drainage survey, asbestos survey or structural opening up.
  • Planning. A householder application is currently about £528, and a lawful development certificate costs half that.
  • Building control, party wall surveyors and warranties.
  • Community Infrastructure Levy. Extensions that add less than 100 m² are generally exempt. Larger extensions to your main home can qualify for an exemption, which has to be claimed before work begins. CIL guidance.
  • Somewhere to live. A project of this scale usually means moving out, so add rent, storage and two moves.
  • A further reserve. On an existing building we advise a contingency of 10% to 15% at the outset, reviewed as investigations and design reduce the unknowns. This plan carries £47,954, which is 5%, so holding the same again outside the contract brings the reserve to about 10%.

Contingency is there for what you don't yet know. An excluded item you already know you want should have its own allowance.

VAT on renovation and extension work

Renovation and extension work is generally subject to VAT at 20%, on labour and materials alike. Two reliefs are worth knowing about. Work to a home that has stood empty for at least two years can qualify for a reduced rate of 5%. And the installation of energy-saving materials such as insulation, heat pumps and solar panels is zero-rated until 31 March 2027, returning to 5% afterwards, though the relief is harder to apply when that work is part of a wider building contract. HMRC construction VAT guidance

The construction of a new house can be zero-rated, which is one reason owners sometimes consider demolition and rebuilding. The £201,406 of VAT on this estimate is not a saving waiting to be claimed, though. A rebuild needs its own cost plan, with a complete structure and roof, and it discards the carbon already invested in the existing house. Take advice from your accountant before relying on a particular VAT treatment.

How to keep the budget under control

Set the budget before the design. Tell your architect the real figure, including fees, VAT, somewhere to live and a reserve.

Get a cost plan early. We bring a quantity surveyor in at concept stage, so the first proposals are tested against the budget. The two options in this plan were £57,431 apart before either was developed in detail.

Investigate before you tender. Opening up a ceiling or digging a trial pit at design stage gives you information while there is still time to respond. Finding the same problem on site adds delay as well as the repair.

Fix the brief. A change on paper may take an afternoon. The same change on site can mean wasted materials, extra labour and a longer programme.

Spend on what is difficult to change later. Insulation, airtightness and well-designed junctions need attention while the building is open. Finishes and fittings are easier to revisit.

Tender properly. A complete set of drawings and a clear specification give contractors a common basis to price. Read their exclusions as carefully as their totals.

Start with a Feasibility Study

A Feasibility Study answers three questions in a few weeks: what can be done with your house, what it is likely to cost, and how long it will take. It tests the brief against the building and the budget before you commit to a developed design. Ours cost between £4,000 and £13,000 + VAT, depending on the complexity of the site.

See how a Feasibility Study works

Download our guide to planning a sustainable home extension

If you're planning to renovate and extend a house in London, we'd be glad to talk it through. Please do get in touch with a little about your house, what you want to change and the budget you have in mind.

→ Email us at architects@risedesignstudio.co.uk
→ Or call the studio on 020 3947 5886


RISE Design Studio, Architects, Interior Designers + Sustainability Experts

☉ Architecture for people and planet
☉ Trading since 2011
☉ Company reg no: 08129708
☉ VAT no: GB158316403

Subscribe by email